Tehran (IP) - Managing-Director of Petropars company said that this company participated in the accomplishment of the phases 1,4,5,6,7,8,12 and 19 of the South Pars joint oilfield with the investment of $23 billion.
Tehran (IP) - Turkey's gas imports from Iran were suspended on March 31 due to a pipeline explosion on Turkish soil, Mehdi Jamshidi-Dana head of the Iranian Gas Transmission Company who was at the time head of the Dispatching Management of the National Iranian Gas Company described the reasons for the delay in repairing the damaged pipeline and the future of the gas contract.
Tehran (IP) - The natural gas production of the gas field exceeded 700 million cubic meters daily with the installation of the jacket of Phase 11, the managing director of Pars Oil and Gas Company said.
Hormozgan (IP) – Executive manager of the development plan of South Pars Gas Field Phase13 announced the installation of its last platform in the Persian Gulf.
Bushehr (IP) - The final South Pars Phase 14 platform was installed in Bushehr, southern Iran, by Iranian experts on Saturday, February 1, on the first day of 10-Day Dawn occasion.
Tehran (IP) - Iranian Minister of Petroleum said Iran's Petropars was developing Phase 11 project of South Pars gas field as CNPC International and Total companies had fully abandoned the project.
Bushehr (IP) - The final South Pars Phase 14 platform was loaded in SADRA Marine Industrial Company to be transferred to the installation site.
The Commander of Khatam al-Anbyia Construction Headquarters says selling cheap raw materials to industrial countries and buying expensive goods from them, is a modern form of slavery.
The offshore section of the phases 22 to 24 of Iran's South Pars Gas Field will be completed by the end of March.
A pipeline carrying gas from South Pars offshore gas field was reportedly damaged on Wednesday.